July 23, 2025: The contractor has rescheduled the water shut down on 40th and Zealand avenues for Monday, July 28, weather permitting. The below project notice was distributed to residents on 40th and Zealand that will be impacted by the water shut off.
July 21, 2025: The contractor will complete water hydrant and valve replacements on 40th and Zealand avenues on Thursday, July 24, weather permitting. The below project notices were distributed to residents on 40th and Zealand Ave that will have their water shut off to complete this work.
July 18, 2025: The contractor will begin removals of marked curbs throughout the reclaim and overlay area next week. The below project notice has been sent to residents impacted by curb removals at the end of their driveway.
July 15, 2025 at 1:15 PM: The contractor has completed the water shut down on 39th Avenue. Due to delays on the initial water shut down, the water shut down impacting residents on 40th and Zealand avenues has been postponed until further notice. Additional notice will be hand delivered to impacted residents on 40th and Zealand avenues as soon as this work has been rescheduled.
July 11, 2025: The contractor will complete water hydrant and valve replacements on 39th Avenue and 40th Avenue on Tuesday, July 15, weather permitting. The below project notices were distributed to residents on 39th, 40th and Zealand Ave that will have their water shut off to complete this work.
June 26, 2025: The contractor will start work the week of July 7, weather permitting. They will begin with storm sewer improvements, followed by isolated curb removals and replacements.
May 1, 2025: The contractor, Northwest Asphalt, is scheduled to begin work in late June or early July, weather permitting, starting with reclaim and overlay work in the Northwood Northeast neighborhood. Mill and overlay improvements in the Jaycee Park neighborhood are expected to follow in early August.